How To Calculate the Quantity of Materials (Sand and Cement) Required for 1 Cubic Meter of Cement Mortar

Sometimes on site, we are faced with the problem of calculating for the amount of materials (sand and cement) required in plastering or rendering! This Post is made to tackle this issue!

Today, i want to talk about how you can calculate the quantity of sand and cement required in Mortar
 
As we all know, Mortar used in Plastering is mixed or produced in different proportions which could include: 1:1, 1:2, 1:3, etc. But here i would like to adopt the 1:6 proportion and do analysis based on this proportion.
 
QUANTITY OF CEMENT AND SAND NEEDED IN BRICKLAYING OR RENDERING (Plastering)

 
For the calculation of cement mortar, lets Assume we are to mix for a cubic meter (1m3): I would then provide the steps on calculating these below:
 
 
 

STEPS TO CALCULATE THIS IS FOUND BELOW

 
1. Calculate the dry volume of materials required for 1m3 cement mortar. Considering voids in sands, we assume that materials consists of 60% voids. That is, for 1m3 of wet cement mortar, 1.6m3 of materials are required.
 
2. Now we calculate the volume of materials used in cement mortar based on its proportions.
 
Let’s say, the proportion of cement and sand in mortar is 1:X, where X is the volume of sand required.
 
Then, the volume of sand required for 1:X for 1m3 Cement Mortar will be
 
                                                   
 
3. The Volume of Cement required will be calculated as:
 
 
 
 
                                                   
 
 
 
Since the volume of 1 bag of cement is 0.0347 m3, so the number of bag of cement will be calculated as:
 
                                                 
 
Therefore, if we were to render a cubic meter of Mortar (1m3) with a mix ratio 1:6 (Meaning One Bag Of Cement for 6 Parts Of sand),
 
 
 
The quantity of sand needed here would be
= 1.371m3 (Volume of sand needed)
 
Lets convert this in Headpans and Wheelbarrow (For Small projects)
 
Volume of 1 headpan =0.0175m3
 
Therefore there will be 1.371/0.0175 = 78.5 Headpans
 
But 4 Headpans = 1 wheelbarrow
 
Therefore 78.5/4 = 19.6 or 20 wheelbarrows
 
Quantity of cement = = 0.22857m3
 
Now lets find the number of Bags of Cement since we have known the total Volume required for 1m3
 
(NOTE: Volume of 1 bag of cement = 0.0347m3)
 
But total volume for 1m3 is 0.22857m3
 
Therefore, the number of bags would be
 
BAGS = Calculated volume/fixed Volume Per Bag Of Cement = (0.22857/0.0347)
 
Bags = 6.58
 
So about 6.6 bags would be required for a 1m3 of mortar along with 20 wheelbarrow of sharp sand or 78.5 Head pans of sharp sand!

Please feel free to Share with Friends and criticize this work as it will help me make it better for other readers
 
 
Recommended:  How to Exchange Bitcoin to Naira

Written by admin

Hi, I'm Okpese! It is my job to handle the content aspect of this great organization and I'm determined to ensure you get it all right as long as you're handling a construction project in Nigeria!

3 Comments

Leave a Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

Quantities Needed For A Cubic Meter Of Concrete

How To Calculate The Number Of Blocks Needed For Your Fence Project Measuring 100ft By 60ft